GP-3.01 AWARD OF CONTRACT (SEE GP-2.19)

Written notice of award shall be sent to the successful bidder. A Notice of AwardThe decision by a procurement agency to execute a purchase agreement or Contract after all necessary approvals have been obtained. may be rescinded at any time prior to execution of the Contract by the AdministratorThe chief executive officer of an Administration..


GP-3.02 RETURN OF PROPOSAL GUARANTY

All proposal guaranties, except those of the three lowest bidders, will be returned immediately following opening and the review of the proposals. The guaranty of the three lowest bidders will be returned following the execution of the Contract and approval by the BoardThe Board of Public Works of the State of Maryland., if required. The ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement. has the right to substitute a bid bond for other bid security at any time prior to return of the proposal guaranty.


GP-3.03 PERFORMANCE BOND AND PAYMENT BOND REQUIREMENTS

(a) Acceptable security for performance and payment shall be as stated in COMAR 21.06.07.01B.
(b) Performance and Payment Bonds. A performance and payment bond is required for all construction Contracts in excess of $100,000 each in the amount equal to at least 100 percent of the Contract price. The bonds shall be delivered by the bidder to the AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02. no later than the time the Contract is to be executed. If the bidder fails to deliver the required bonds, his bid shall be rejected, his bid security shall be enforced, and award of the Contract may be made to the next lowest responsive and responsible bidder.
(1) The required performance bond shall be in the form specified in COMAR 21.07.02.10, Exhibit A.
(2) The required payment bond shall be in the form specified in COMAR 21.07.02.10, Exhibit B.


GP-3.04 EXECUTION OF CONTRACT

(a) The Contract shall be effective only upon receipt by the AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02. of the proper, executed Contract form, and performance and payment bonds (if required), approval by the BoardThe Board of Public Works of the State of Maryland. of Public Works, (if required), and execution of the Contract by the AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02..
(b) After a Notice of AwardThe decision by a procurement agency to execute a purchase agreement or Contract after all necessary approvals have been obtained., as provided in GP-3.01, has been issued to a bidder, the AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02. shall forward the formal Contract form and the appropriate forms for the payment and performance bonds (if any) to the bidder for execution. The bidder will execute the Contract form and return same, together with fully executed payment and performance bonds (if any), to the AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02. within 10 days after receipt of same. After receipt of properly executed Contract form and payment and performance bonds, (if any), the AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02. will execute the Contract within 60 days and forward the bidder a copy; provided, however, that the BoardThe Board of Public Works of the State of Maryland. has approved the Contract if such approval is required. If the AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02. fails to execute the Contract and the period of irrevocability has expired, the bidder may, as its sole remedy, withdraw its bid.

GP-3.05 FAILURE TO EXECUTE CONTRACT

Failure of the bidder to execute the Contract and file acceptable security as defined in GP-3.03 within the time aforesaid shall be just cause for the annulment of the award and the forfeiture of the proposal guaranty which shall become the property of the State of Maryland, not as a penalty but in liquidation of damages sustained. AwardThe decision by a procurement agency to execute a purchase agreement or Contract after all necessary approvals have been obtained. may then be made to the next lowest responsive, responsible bidder or the work may be readvertised and constructed under Contract or otherwise, as the AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02. may decide.