499 WORKING DRAWINGS

From MDOT Policy Manual
Jump to: navigation, search
499.01 DESCRIPTION.
Schedule and distribute working drawings, which are described in TC-1.03 and specified in TC-4.01. Working drawings shall exhibit good drafting practices and represent the original work of the ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement., fabricator, or supplier. Duplicated portions of the PlansThe official drawings issued by the Administration as part of the Contract Documents, including those incorporated in the Contract Documents by reference. will not be accepted. When requested by the AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02. or consultant, submit calculations or other information deemed necessary to backup working drawings. Calculations and other backup material shall be signed and sealed by a professional engineer registered in the State of Maryland.
499.02 MATERIALS.
Not applicable.
499.03 CONSTRUCTION.
499.03.01 Schedule. As a first order of work, prepare and submit a schedule for the submission of the working drawings as specified in 499.03.02 or 499.03.03. Coordinate the schedule with and in full accord with the Progress Schedule submitted to the procurement officer as specified in GP-8.04 and TC-5.02.
The schedule shall include each type of working drawings (e.g. form plans, structural steel, etc.), approximate number of drawings to be reviewed, estimated date of first submission, and estimated rate of submission of drawings (e.g. 5/wk). Where possible, submit the most crucial drawings first with sufficient time for review so as to minimize delays during construction.
499.03.02 Consultant Engineering Firm. When the Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof specify that a consultant engineering firm is to review the working drawings for the structure, send all working drawings to that firm.
To expedite the checking and distribution of working drawings, fabricators or suppliers may send prints directly to the appropriate consultant engineering firm with copies of all correspondence to the ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement., Director - Office of StructuresBridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, end walls, buildings, sewers, service pipes, underdrains, foundation drains, steps, fences, and other features that may be encountered in the work and not otherwise classified., and the District EngineerAny person designated by the Administrator or the procurement officer, acting directly or through his duly authorized representative, such representative acting within the scope of the particular duties assigned to him or of the authority given him.. If the ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement. requests that all plans be routed through the ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement.’s office, then the establishment of that procedure should be the first order of work so as to avoid possible misunderstandings as to the processing. Be advised that this plan of action will delay the turn around time and will not constitute grounds for complaint or a time extension.
The ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement., fabricator, or supplier shall furnish to the consultant engineering firm 10 prints each of all working drawings, etc., for primary review.
Once primary review is complete, the ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement., fabricator, or supplier shall furnish to the consultant engineering firm additional prints (number to be furnished by primary reviewer) for stamping and forwarding to the AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02.’s Office of StructuresBridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, end walls, buildings, sewers, service pipes, underdrains, foundation drains, steps, fences, and other features that may be encountered in the work and not otherwise classified. for secondary review and distribution.
All working drawings for the structures will not be considered accepted until they bear the acceptance stamps of both the consultant engineering firm and the AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02.’s Office of StructuresBridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, end walls, buildings, sewers, service pipes, underdrains, foundation drains, steps, fences, and other features that may be encountered in the work and not otherwise classified..
499.03.03 Office of StructuresBridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, end walls, buildings, sewers, service pipes, underdrains, foundation drains, steps, fences, and other features that may be encountered in the work and not otherwise classified.. When no consultant engineering firm is specified, send all working drawings for the structures to the Director - Office of StructuresBridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, end walls, buildings, sewers, service pipes, underdrains, foundation drains, steps, fences, and other features that may be encountered in the work and not otherwise classified..
To expedite the checking and distribution of working drawings, fabricators or suppliers may send prints directly to the Director with copies of all correspondence to the ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement. and the District EngineerAny person designated by the Administrator or the procurement officer, acting directly or through his duly authorized representative, such representative acting within the scope of the particular duties assigned to him or of the authority given him.. If the ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement. requests that all drawings be routed through the ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement.’s office, then the establishment of that procedure should be the first order of work so as to avoid possible misunderstandings as to the processing. Be advised that this plan of action will delay the turn around time and will not constitute grounds for complaint or a time extension.
The ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement., fabricator, or supplier shall furnish to the Director 10 prints each of all working drawings, etc., for primary review.
Once primary review is complete the ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement., fabricator, or supplier shall furnish to the Director additional prints (number to be furnished by primary reviewer) for final review and distribution.
499.03.04 Revisions and Substitutions. All modifications, regardless of whether or not the Contract includes a consultant engineering firm, shall be sent to the Director - Office of StructuresBridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, end walls, buildings, sewers, service pipes, underdrains, foundation drains, steps, fences, and other features that may be encountered in the work and not otherwise classified. for acceptance. Any modifications implemented, without written acceptance from the Director - Office of StructuresBridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, end walls, buildings, sewers, service pipes, underdrains, foundation drains, steps, fences, and other features that may be encountered in the work and not otherwise classified., will be subject to the requirements of GP-5.02.
499.04 MEASUREMENT AND PAYMENT.
This work will not be measured but the cost will be incidental to other pertinent items.