460.01 DESCRIPTION.
Furnish, fabricate, and install preformed joint fillers, preformed elastomeric joint seals, troughs, structural steel, and metal plates to be utilized in providing expansion and contraction capabilities in structures.
460.02 MATERIALS.
Structural Steel       909, A 709, Grade 36
Hardware for Drainage Troughs       909.06
Preformed Joint Fillers       911.02
Preformed Polychloroprene Elastomeric Compression Joint Seals       911.04
Lubricant Adhesive       911.04.03
Troughs       911.11
All structural steel for drainage troughs shall be hot dip galvanized to meet A 123 and A 153.
Ensure that troughs meet the thickness requirements for the type of material supplied. Place joints and splices for drainage troughs only where specified.
460.02.01 Paint. Refer to Section 435.
460.03 CONSTRUCTION.
Store expansion joint material delivered to the bridge site under cover on platforms at least 4 in. above all types of surfaces and vegetation. Protect it at all times from damage and when placed ensure that it is free from dirt, oil, grease, or other foreign substances. All welding shall meet AWSAmerican Welding Society D1.1 unless otherwise specified. All material and installation methods shall be approved prior to installation of any expansion joint material.
Provide the longest possible lengths of the preformed material with a minimum of joints. Lengths less than 4 ft shall be one piece. Cut material to a clean, true edge. Ensure straight lines at the joint.
When installing the seal, do not use any type of equipment that will damage the seal. Remove and replace damaged seals.
Cleaning And Painting. Refer to Section 435.
Joint Replacement and Modification. Where the Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof specify replacement or modification to existing expansion joints on bridges on which traffic will be maintained, have available a supply of steel plates at least 4 x 8 ft and 1 in. thick. Place these plates over the joints if traffic has to be restored before the concrete has cured and at any time the unfinished work will interfere with traffic.
Where the Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof specify modification to existing expansion joints, remove the concrete as specified in 405.03.
Where the Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof only specify replacement of existing roadway joint seal, the work shall include cleaning and painting the joint.
Thoroughly clean existing drainage troughs to remove of all debris. Clean and paint all exposed metal where noted on the PlansThe official drawings issued by the Administration as part of the Contract Documents, including those incorporated in the Contract Documents by reference. or as directed.
All angles shall be cut with a saw. All holes and slots shall be drilled. Do not cut with a torch.
Power tool clean to bare metal and paint any areas where the existing steel coating is damaged due to the installation of new troughs.
After the joints are complete in place and just prior to placing the compression seal, remove the masking tape and residue, and install the seal. Then apply the finish coat to the exposed portion of the angles above the seal.
Joint Seals in BridgeA structure including supports erected over a depression or an obstruction, such as water, highway, or railway, and having a track or passageway for carrying traffic or other moving loads, and having an opening measured along the center of the roadway of more than 20 feet between undercopings of abutments or spring lines of arches, or extreme ends of openings for multiple boxes; it may also include multiple pipes, where the clear distance between openings is less than half of the smaller contiguous opening. For lengths, all dimensions shall be parallel to the center line of the roadway. The dimensions of handrails will not be taken into account in measuring bridge lengths. Any bridge or highway grade separation structure includes the connecting highways, substructure, superstructure, roadway approaches, entrance plazas, interchanges, overpasses, underpasses, and other structures which the Administration may deem necessary together with all property rights, easements, franchises, and interests acquired by the Administration for the construction and operation of the bridge. Decks. Place transverse compression seals in one piece for the entire length of the roadway joint. Shop and field splices are prohibited. Use the longest compression seal pieces as practicable for longitudinal bridge joints.
Apply the lubricant adhesive according to the manufacturer’s recommendations. If the seal is stretched in excess of 5 percent, remove and reinstall the seal as directed.
460.03.01 In-Place Testing. Subject the completed joint to a water test to detect any leakage. Conduct the test at least five days after completing the joint. Provide all facilities required for the EngineerAny person designated by the Administrator or the procurement officer, acting directly or through his duly authorized representative, such representative acting within the scope of the particular duties assigned to him or of the authority given him.’s inspections of the underdeck areas. Cover the roadway section of the joint from curb to curb, or parapet to parapet, with at least 1 in. of water. If this is not possible, perform the water test in part section along the joint. When testing subsequent part sections, overlap at least 1 ft of the joint previously tested.
Maintain the ponding for a period of five hours for the entire roadway or each section of joint being tested. During and at the conclusion of the test, examine the underside of the joint for leakage. The expansion joint seal will be considered watertight if no obvious wetness is visible. If the joint system exhibits evidence of water leakage at any point, locate and repair all leaks.
When repairs are required, perform a subsequent water test.
If the joint leaks after the second test, remove, replace, and retest the seal.
460.04 MEASUREMENT AND PAYMENT.
The payment will be full compensation for furnishing, fabricating, and placing structural steel, roadway seals, drainage troughs, catch basins, downspouts, cleaning, painting, and all material, labor, equipment, tools and incidentals necessary to complete the work.
460.04.01 Joints in structures will not be measured but the cost will be incidental to the pertinent SuperstructureAll of that part of the structure above bottoms of bearings of simple and continuous spans, skewbacks of arches and tops of footings of rigid frames, except as noted above for substructure. Concrete item.
460.04.02 When an item for Modifying Existing BridgeA structure including supports erected over a depression or an obstruction, such as water, highway, or railway, and having a track or passageway for carrying traffic or other moving loads, and having an opening measured along the center of the roadway of more than 20 feet between undercopings of abutments or spring lines of arches, or extreme ends of openings for multiple boxes; it may also include multiple pipes, where the clear distance between openings is less than half of the smaller contiguous opening. For lengths, all dimensions shall be parallel to the center line of the roadway. The dimensions of handrails will not be taken into account in measuring bridge lengths. Any bridge or highway grade separation structure includes the connecting highways, substructure, superstructure, roadway approaches, entrance plazas, interchanges, overpasses, underpasses, and other structures which the Administration may deem necessary together with all property rights, easements, franchises, and interests acquired by the Administration for the construction and operation of the bridge. Roadway Joints is included in the Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof, the cost of furnishing, fabricating, and placing new structural steel, new roadway seals, modifying existing joints on bridge roadway including saw cutting and removal of existing concrete, new concrete, steel plates, cutting of existing steel, welding, drainage troughs, catch basins, downspouts, etc., shall also be included in the Contract unit price per linear foot for the item. The measurement will include the horizontal distance from the inside face to inside face of parapets plus the vertical distance of the curb faces and parapets.
460.04.03 When an item for Drainage Trough for BridgeA structure including supports erected over a depression or an obstruction, such as water, highway, or railway, and having a track or passageway for carrying traffic or other moving loads, and having an opening measured along the center of the roadway of more than 20 feet between undercopings of abutments or spring lines of arches, or extreme ends of openings for multiple boxes; it may also include multiple pipes, where the clear distance between openings is less than half of the smaller contiguous opening. For lengths, all dimensions shall be parallel to the center line of the roadway. The dimensions of handrails will not be taken into account in measuring bridge lengths. Any bridge or highway grade separation structure includes the connecting highways, substructure, superstructure, roadway approaches, entrance plazas, interchanges, overpasses, underpasses, and other structures which the Administration may deem necessary together with all property rights, easements, franchises, and interests acquired by the Administration for the construction and operation of the bridge. is included in the Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof, the furnishing and placing of drainage troughs including catch basins, downspouts, structural steel, and hardware will be measured and paid for at the pertinent Contract unit price per linear foot. This price will include cutting of angles, cleaning, painting, drilling of concrete, expansion bolts, etc. The measurement will be the center line distance from end to end of the installed drainage trough fabric.
460.04.04 Cleaning existing drainage troughs and cleaning and painting metal attachments will not be measured but the cost will be incidental to other pertinent items.