303 PIPE CULVERTS

From MDOT Policy Manual
Jump to: navigation, search
303.01 DESCRIPTION.
Furnish and install pipe culverts, make connections to miscellaneous structures and other pipe culverts, reinstall existing pipes, remove existing pipe culverts, abandon existing pipes, and clean existing pipes.
303.02 MATERIALS.
No. 57 Aggregate       901.01
Crusher Run Aggregate CR-6       901.01
Portland Cement Concrete       902.10, Mix No. 2
Controlled Low Strength Material       902.16
Curing Compound       902.07.03
Grout       902.11
Brick       903.03
Mortar       903.06
Pipe       905
Select Borrow       916.01
Common Borrow       916.01
Stormwater Management (SWMStormwater Management) Facility Embankment Clay Core Borrow       916.01
Water       921.01
Detectable Utility Marking Tape       Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof
Bedding. Use earth meeting the requirements of M 145, A-1, A-2-4, A-2-5 or A-3. The maximum particle size is 1.25 in. Do not use organic material, stones larger than 1.5 in., or frozen lumps. Selected Backfill may be used.
Backfill. Use material meeting the requirements for Select Borrow, Selected Backfill or Controlled Low Strength Material (Flowable Backfill). Large lumps, clods, frozen material or rocks are not acceptable. For plastic pipe installations, use backfill materials meeting the requirements of M 145, A-1, A-2-4, A-2-5 or A-3
303.03 CONSTRUCTION.
303.03.01 Pipe CulvertAny structure not classified as a bridge which provides an opening under any roadway. Installation.
When endwalls are visible from the roadway, construct them parallel to the roadway with the askew pipe protruding through the end wall. If not visible, construct them normal to the center line of the pipe.
Clean existing pipes and dispose of the material.
TrenchAn excavation made for the purpose of installing or removing pipes, drains, catch basins, etc., which is later refilled. Excavation. When a pipe is to be laid on existing ground, on or under fill, construct embankment to a height of at least 9 in., but not more than 3 ft above the proposed top of the pipe.
Excavate, to a depth at least 4 in. below the bottom of pipe. When rippable rock is encountered, remove rocks, boulders, and other hard, lumpy, or unyielding material to a depth of at least 12 in. below the bottom of the outer diameter of the pipe. When non-rippable rock is encountered, remove it to a depth of at least 8 in. below the outer diameter of the pipe. Handle excavated material in accordance with 402.03.01.
Ensure trench width is at least twice the outside diameter of the pipe or the outside diameter plus 18 in. on each side, whichever is less. Ensure trench sides are vertical up to at least the midpoint of the pipe to be installed.
(a) Prepare TrenchAn excavation made for the purpose of installing or removing pipes, drains, catch basins, etc., which is later refilled. SubgradeThe top surface of a roadbed upon which the pavement structure, shoulders, and curbs are constructed.. Fine grade and compact the subgrade to at least 97 percent of the maximum dry density per T 180. Remove and dispose of all soft and unstable material and all other portions of the subgrade that will not properly compact in accordance with Section 301. Replace with selected backfill and compact. Obtain subgrade approval in accordance with 208.03.05.
(b) Bedding. After preparing the trench subgrade, place pipe bedding backfill and compact. Ensure that the moisture content is in the rage of optimum content to obtain thorough compaction.
Place bedding for culverts that are 48 in. or more in nominal horizontal diameter in an approved foundation, shaped using a template that supports the pipe for at least 10 percent of its overall height.
For pipe culverts installed in stormwater management (SWMStormwater Management) facility embankments, place pipe culverts on bedding matching the type and quality conforming to that specified for the surrounding fill material. Ensure pipe culverts are firmly and uniformly bedded throughout the entire length. Perform the work in the presence of the SWMStormwater Management facility As-Built (AB) InspectorThe authorized representative of the procurement officer assigned to make detailed inspection of any or all portions of the work, or materials therefore..
(c) Laying of Pipes. Lay pipes with hubs upgrade. A single lay hole through the shell of concrete pipe is acceptable with an approved lifting device. Ensure the lay hole is cast in the pipe during fabrication or core it without damaging or exposing any reinforcement. After installation, permanently seal the lay hole by filling with mortar, rubber plug, or other approved means. Wood plugs may not be used. Lay holes that expose any reinforcement are not acceptable. Do not lay pipe in standing water or when weather conditions are deemed unsuitable by the EngineerAny person designated by the Administrator or the procurement officer, acting directly or through his duly authorized representative, such representative acting within the scope of the particular duties assigned to him or of the authority given him..
(d) Joints. Seal pipe joints in a manner appropriate for the applicable pipe material.
(1) Reinforced Concrete Pipe. Seal circular pipe joints using rubber gaskets meeting C 433. Seal elliptical pipe joints using preformed flexible joint sealants meeting C 990.
(2) Metal Pipe. Use bell and spigot joints with integral rubber gaskets or butt pipes and seal using rubber gaskets with an approved coupling band meeting 905.01.
(3) Plastic Pipe. Use integral bell and spigot joints with flexible elastomeric seals meeting D 3212.
(e) Backfill. Ensure all joints have been sealed and are water-tight before placing backfill material. When pipe culverts are installed through SWMStormwater Management facility embankments, use material matching the type and quality conforming to that specified for the surrounding fill material. The presence of large lumps, clods, frozen material, or rocks in the backfill are unacceptable.
Place backfill material along the side of the pipe for the full width of the trench in layers not exceeding an uncompacted depth of 6 in. Compact each layer simultaneously on both sides of the pipe using an approved mechanical tamper and according to Section 210. Compact thoroughly under the haunches of the pipe. Continue this method of filling and compacting until the compacted backfill material is at least 9 in. above the top of the pipe for concrete and metal pipe and at least 12 in. above the top of the pipe for plastic pipe. Prevent damage by heavy loads, equipment, and vehicular traffic. Replace any defective or damaged pipe.
Where specified or directed, backfill using Flowable Backfill according to Section 314.
For pipe culverts installed through SWMStormwater Management facility embankments with a clay core, place backfill around pipe culverts concurrently with clay core and embankment material adjacent to the pipe trench. Place backfill along the sides of the pipe in layers not exceeding an uncompacted depth of 4 in. Compact each layer simultaneously on both sides of the pipe and with core and embankment materials. Compact material around the pipe using hand tampers or approved mechanical tampers and ensure thorough compaction of material under pipe haunches. Continue this method of filling and compacting until the backfill is completed to at least 8 in. above the top of pipe. Perform the work in the presence of the SWMStormwater Management facility As-Built (AB) InspectorThe authorized representative of the procurement officer assigned to make detailed inspection of any or all portions of the work, or materials therefore..
Protect pipes from damage due to construction activities. Do not drive equipment within 4 ft when measured horizontally from the pipe nor drive equipment over the pipe until at least 24 in. of compacted fill is over the pipe.
Place detectable utility marking tape in the trench immediately above the structural backfill. Demark the tape as to its purpose, i.e., "STORM DRAIN".
(f) Inspection and Acceptance. Within 30 days following installation, and in the presence of the EngineerAny person designated by the Administrator or the procurement officer, acting directly or through his duly authorized representative, such representative acting within the scope of the particular duties assigned to him or of the authority given him., visually inspect all pipe culverts. Any cracks, differential movement, efflorescence, rust stains, spalls, exposed reinforcement, slabbing, dents, buckling, holes, damaged coating, obstructions, improperly engaged joints, improper gasket placement, excessive joint gaps, misaligned joints, excessive deflection, or undue horizontal or vertical misalignment will be cause for repair or replacement. Video inspect pipe which cannot be physically accessed for inspection. Ensure that thermoplastic pipe deflection does not exceed 5 percent.
303.03.02 Mid-Pipe Pipe CulvertAny structure not classified as a bridge which provides an opening under any roadway. Connections. Pipe connections may be either prefabricated or constructed in the field. Use a prefabricated connection unless specified or directed.
For reinforced concrete pipes connecting to other reinforced concrete pipes, a field pipe connection includes cutting a hole in one pipe, inserting and trimming the connecting pipe, and placing a concrete collar using Concrete Mix No. 2 at the connection. Finish the connection to provide a smooth surface.
For corrugated metal pipes, a welded connection may be substituted for the concrete collar when the connection is to other corrugated metal pipes. Coat the weld with a zinc rich paint coating per M 36. For connections to drainage structures, refer to 305.03.05.
For plastic pipes, use a prefabricated plastic connection matching the pipe material.
When dissimilar pipe materials are encountered, use a junction box according to Section 305.
303.03.03 Pipe CulvertAny structure not classified as a bridge which provides an opening under any roadway. Encasement. When specified, encase pipes using Concrete Mix No. 2.
303.03.04 Removal of Existing Pipe Culverts. When specified, remove and dispose of existing pipe culverts. Use backfill material that is similar to the adjacent material and compact according to Section 208, Section 210, or Section 701, whichever is applicable.
303.03.05 Reinstallation of Existing Pipe Culverts. When specified, remove, salvage, and reinstall pipe culverts according to 303.03.01.
303.03.06 Abandoned Pipe Culverts. Plug abandoned pipe culverts using Concrete Mix No. 2 or brick masonry according to 463.03. Fill pipes with Flowable Backfill according to Section 314.
303.03.07 Clean Existing Pipe Culverts. When specified, clean existing pipe culverts, removing all sediment and debris without damaging the pipe, pipe joints, or connecting structures. Remove and dispose of sediment and debris according to Section 308.
303.04 MEASUREMENT AND PAYMENT.
The payment will be full compensation for all applicable excavation, sheeting, shoring, dewatering, hauling, , storing, rehandling of material, removal and disposal of excess and unsuitable material, tamped fill, forming bed, foundation, grouting, masonry, bedding, pipe, backfill, compaction, inspection, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
303.04.01 New pipe culverts will be measured complete in place and paid for at the Contract unit price per linear foot for the pertinent size and type of pipe. When a new pipe is installed in the same location as an existing pipe, the cost of removal and disposal of the existing pipe, including end walls and end sections, will not be measured but the cost will be incidental to the Contract price of new pipe.
Detectable utility marking tape will not be measured but will be incidental to the Contract price of pertinent pipe item.
303.04.02 Pipe connections will be measured and paid for at the Contract unit price per each for the pertinent size and type of pipe connection. No deduction from the new pipe measurement will be made for pipe connections. Connections to drainage structures with prefabricated holes in which the pipe will be connected with grout or mortar will not be measured, but the cost will be incidental to the pertinent pipe culvert item.
303.04.03 Pipe elbows will be measured and paid for at the Contract unit price per each for the pertinent size and type of pipe elbow.
303.04.04 Excavation required below the planned elevation will be measured and paid for as specified in 301.04.
303.04.05 Selected Backfill will be measured and paid for as specified in Section 302.04.
303.04.06 Flowable Backfill will be measured and paid for as specified in Section 314.04.
303.04.07 Select Borrow will be measured and paid for as specified in Section 203.04.
303.04.09 Common Borrow will be measured and paid for as specified in Section 203.04.
303.04.10 Pipe Bedding Backfill will be measured and paid for at the Contract unit price per cubic yard.
303.04.11 Stormwater Management (SWMStormwater Management) Facility Embankment Clay Core Borrow will be measured and paid for at the Contract unit price per cubic yard.
303.04.12 Pipe culvert encasement will be measured and paid for at the Contract unit price per cubic yard of Mix 2 Concrete for Miscellaneous StructuresBridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, end walls, buildings, sewers, service pipes, underdrains, foundation drains, steps, fences, and other features that may be encountered in the work and not otherwise classified..
303.04.13 Removal of Existing Pipe will be measured and paid for at the Contract unit price per linear foot. The size and type of pipe will not be measured but will be incidental to the Contract unit price. Removal of existing end walls and existing end sections associated with the pipe will not be measured but the cost will be incidental to the Contract price.
303.04.14 Reinstallation of existing pipe culverts will be measured and paid for at the Contract unit price per linear foot for Relaid Existing Pipe Culverts Any Size. The size and type of pipe will not be measured but will be incidental to the Contract price.
303.04.15 Abandoned pipe culverts will be measured and paid for at the Contract unit price per cubic yard for Flowable Backfill for Pipe Abandonment.
303.04.16 Plugs for abandoned pipe culverts and plugs to create a permanent blockage of the flow of water will be measured and paid for at the Contract unit price per cubic yard of Mix 2 Concrete for Miscellaneous StructuresBridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, end walls, buildings, sewers, service pipes, underdrains, foundation drains, steps, fences, and other features that may be encountered in the work and not otherwise classified. or Brick Masonry for Miscellaneous StructuresBridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, end walls, buildings, sewers, service pipes, underdrains, foundation drains, steps, fences, and other features that may be encountered in the work and not otherwise classified..
303.04.17 Cleaning existing pipe culverts will be measured and paid for at the Contract unit price per linear foot for Clean Existing Pipe Any Size. The size and type of pipe will not be measured but will be incidental to the Contract price. Removal of construction debris and sediment will not be measured for payment.