302 SELECTED BACKFILL

From MDOT Policy Manual
Jump to: navigation, search
302.01 DESCRIPTION.
Place selected backfill material and compact.
302.02 MATERIALS.
No. 57 Aggregate       901.01
Crusher Run Aggregate CR-6       901.01
302.03 CONSTRUCTION.
Place selected backfill on suitable subgrade material that has been prepared in according to Section 208 and compact the selected backfill according to Section 210. When unsuitable subgrade material is encountered, notify the EngineerAny person designated by the Administrator or the procurement officer, acting directly or through his duly authorized representative, such representative acting within the scope of the particular duties assigned to him or of the authority given him. to inspect the material. Excavate unsuitable material according to 208.03.01 and Section 301 before placing selected backfill.
302.04 MEASUREMENT AND PAYMENT.
Selected Backfill using No. 57 Aggregate or Selected Backfill using Crusher Run Aggregate CR 6 will be measured and paid for at the Contract unit price per cubic yard. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work.