206 REMOVAL OF EXISTING PAVEMENT, SIDEWALK, PAVED DITCHES, CURB, OR COMBINATION CURB AND GUTTER

From MDOT Policy Manual
Jump to: navigation, search
206.01 DESCRIPTION.
Remove to full depth and dispose of existing pavement, sidewalk, paved ditches, curb, or combination curb and gutter.
206.02 MATERIALS.
Not applicable.
206.03 CONSTRUCTION.
206.03.01 Full Depth Saw Cut. Saw cut to full depth the existing pavement, sidewalk, paved ditches, curb, or combination curb and gutter along the lines specified or as directed.
206.03.02 Use of Removed Pavement, SidewalkThe portion of the roadway constructed for use by pedestrians., Paved Ditches, Curb, or Combination Curb and Gutter. When approved, removed materials may be broken and used in the work. Refer to 204.02.01.
206.03.03 Protection of Retained Pavement, SidewalkThe portion of the roadway constructed for use by pedestrians., Paved Ditches, Curb, or Combination Curb and Gutter. Protect all sections designated to remain from being damaged. Repair or replace damaged areas.
206.04 MEASUREMENT AND PAYMENT.
The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work.
206.04.01  Removal of existing pavement, sidewalk, paved ditches, curb or combination curb and gutter, and full depth saw cuts within the limits of any class of excavation will not be measured but the cost will be incidental to the Contract unit price for the Class of Excavation in which it occurs.
206.04.02 Saw cuts, removal of existing pavement, sidewalk (except as specified in 603.04), paved ditches, and curb or combination curb and gutter (except as specified in 602.04) outside the limits of any class of excavation will be measured in the original position and paid for as follows:
(a) Saw Cuts per linear foot when an item is included in the Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof.
(b) Removal of Existing Pavement, SidewalkThe portion of the roadway constructed for use by pedestrians., and Paved Ditches per cubic yard.
(c) Removal of Existing Curb or Combination Curb and Gutter per linear foot.
When any material included in (b) or (c) is removed but not replaced, backfilling and landscaping as directed by the EngineerAny person designated by the Administrator or the procurement officer, acting directly or through his duly authorized representative, such representative acting within the scope of the particular duties assigned to him or of the authority given him. will not be included in Contract Unit Price. Payment for this work will be made using the applicable items included in the Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof.