202 CHANNEL OR STREAM CHANGE EXCAVATION (CLASS 5)

From MDOT Policy Manual
Jump to: navigation, search
202.01 DESCRIPTION.
Excavate for changes in channels or streams when specified. Use all suitable material for the construction of the project. Dispose of unsuitable material as directed.
202.02 MATERIALS.
Not applicable.
202.03 CONSTRUCTION.
Section 201.
202.04 MEASUREMENT AND PAYMENT.
Class 5 Excavation will be measured and paid for at the Contract unit price per cubic yard. The payment will be full compensation for all excavation and hauling, formation and compaction of embankments and backfill, backfilling old stream beds or otherwise disposing of excess and unsuitable materials, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
Material will be measured in its original position and the volume computed by the Method of Average End Area. The cross sectional area measured will not include liquids. Measurement for Class 5 Excavation excludes any material removed outside the limits of payment as specified in the Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof.