106 ASPHALT MIXES FOR MAINTENANCE OF TRAFFIC

From MDOT Policy Manual
Jump to: navigation, search
106.01 DESCRIPTION.
Place asphalt mix for maintenance of traffic.
106.02 MATERIALS.
Tack Coat (Rapid Setting)       904.03
Asphalt mix       904.04
Crack Filler       911.01 & 911.01.01
Production Plant       915
106.03 CONSTRUCTION.
Refer to 504.03.
106.04 MEASUREMENT AND PAYMENT.
Asphalt mixes for Maintenance of Traffic will be measured and paid for at the Contract unit price per ton. The payment will be full compensation for all tack coat, crack filler, hauling, placing, compacting, maintaining, removal, rehandling, reworking, disposal, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
When an asphalt mix is part of any base or pavement course used for the construction and maintenance of temporary detours, approaches, crossings, and widenings, the item of work will be measured and paid for as specified in Section 504. For payment of temporary tie-ins, refer to 504.04.
Asphalt mixes for maintenance of traffic when used for temporary and permanent patching at pipe culverts and utilities will not be measured but the cost will be incidental to the Contract unit price for Pipe CulvertAny structure not classified as a bridge which provides an opening under any roadway. or Utility item.