102.01 DESCRIPTION.
Remove and dispose of existing buildings, including foundations, footings, or any part thereof, and backfill as specified. Locations of buildings included in the work will be designated in the Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof by the circled numbers ①,②, ③ etc.
102.02 MATERIALS.
Not applicable.
102.03 CONSTRUCTION.
Schedule the removal, razing, or occupation of buildings and appurtenances as one of the first items of work. Post and protect the buildings from vandalism and theft.
Remove and dispose of buildings scheduled for temporary use immediately when vacated.
Buildings and appurtenances may be disposed of by burning if they are not located close to habitable dwellings and if not prohibited by local or State laws, regulations, ordinances, or by the fire marshal.
Salvaged materials shall become the property of the ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement.. Selling of merchantable material and removal by the purchaser shall be done only during daylight working hours and accompanied by a ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement.'s representative.
102.04 MEASUREMENT AND PAYMENT.
Removal and Disposal of Existing Buildings will not be measured but will be paid for at the Contract lump sum price. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work. Buildings not designated for removal and disposal in the Contract DocumentsThe written agreement executed between an Administration and the successful bidder, covering the performance of the work and furnishing of labor, equipment and materials, by which the Contractor is bound to perform the work and furnish the labor, equipment and materials, and by which the Administration is obligated to compensate him therefore at the mutually established and accepted rate or price. The Contract Documents shall include the Invitation for Bids, Notice to Contractors, Instructions to Bidders, Proposal, Contract Forms and Bonds, General Provisions, Specifications, Supplemental Specifications, all Special Provisions, all Technical Provisions, all Plans and Notices to Proceed, also any written Change Orders and Supplemental Agreements that are required to complete the construction of the work in an acceptable manner, including authorized extension thereof will not be measured but the cost will be incidental to Section 101. The AdministrationShall mean any one of the Administrations within the Maryland Department of Transportation, as listed in GP 1.02. reserves the right to eliminate from this item any or all buildings or structures. For each building eliminated from this item, the item will be credited to the extent of the cost eliminated, which will be determined from a breakdown submitted by the ContractorAny person having a Contract with a procurement agency. Contractor does not include an employee with an employment Contract, or an employee organization with a collective bargaining agreement. showing the tabulation of individual unit costs used in arriving at the Contract price for this item. Submit a breakdown of the Contract lump sum price for Removal and Disposal of Existing Buildings to the EngineerAny person designated by the Administrator or the procurement officer, acting directly or through his duly authorized representative, such representative acting within the scope of the particular duties assigned to him or of the authority given him. prior to beginning work.